Project/Engagement Details
Regency Centers required analysis and migration of approximately 35 SharePoint sites from SharePoint 2010 to SharePoint 2019. This consisted of analysis of the refined site list provided by Regency, prioritization of sites to be reviewed and migrated, configuration/development, assistance with content migration, aid with user acceptance, training and go-live, and completion of the migration prior to April 2021.
After the initial analysis and completion of the technical architecture design, TEAM IM recommended utilizing an agile multiple sprint approach toward the migration of SharePoint sites. TEAM IM worked in partnership with Regency resources, including the migration of content through two development (Agile) work sprints. This included:
• Completion of a discovery analysis on the prioritized SharePoint site list
• Providing feedback on initial analysis and updated timeline to complete the migration
• Completing the Technical Architecture Design document
• Installation/Configuration and testing of the SharePoint 2019 server based on the output of the technical architecture design document
• Completing content migration of selected SharePoint simple sites through Sprint 1
• Completing content migration of identified complex SharePoint sites through Sprint 2
• Assisting Regency with additional requirements like content migration of other sites, user training, user acceptance testing, go-live, and ongoing enhanced support